Village Hall Refurbishment Phase One Update

The Village Hall Committee are pleased to announce that the work is well underway for the Phase One Refurbishment. There was an issue with the roof which has been successfully resolved with this work due to be completed shortly

The additional room requires its final coat of plastering prior to painting and although temporary stairs kindly put in by the builders, Spencer Francis, this room will be used for storage until a later phase of the refurbishment programme

Under the supervision of Ray Collins we are currently looking to finish the inside of the main Hall with a painting programme and will be finished before the first booking on 10th January

 

Undercoat going on

 

First Coat now taking place

Second Coat and Gloss Work

Starting on the Doctors Waiting Room now

Floor getting a polish now